Subject: RE: 200328 - Vastern Court, Caversham Road, Reading
(Extension of time)
From: Marie Jasper <marie.jasper@bartonwillmore.co.uk>
Sent: 21 December 2021 16:24
To: Conlon, Brian <Brian.Conlon@reading.gov.uk>
Cc: Eatough, Richard <Richard.Eatough@reading.gov.uk>
Subject: RE: 200328 - Vastern Court, Caversham Road, Reading (Extension
of time)
Dear Brian,
Further to
your email below, as requested, we write to confirm the reason Aviva has issued
a “pre notification of appeal” in relation to the Reading Station Park outline
planning application (Ref: 200328).
The
application was originally submitted on 26th February 2020 with
amendments submitted on 8th October 2021.
The
amendments are minor in nature and do not result in any significant new or
different impacts, but positively respond to comments from RBC and consultees,
in order to improve the scheme.
As such,
given the original submission date, and time RBC and consultees have had to
consider the proposals, it was anticipated that following submission of the
amendments, the application would be progressed to committee at the earliest
opportunity. However, during our discussions on 1st and 26th
November 2021 there was a lack of any clear confirmation regarding the
timetable for determination or the likelihood of an officer’s recommendation of
approval. Furthermore, it was suggested that officers intended to
await the outcome of the Berkeley’s appeal in relation to 55 Vastern Road (Ref:
200188) before discussing Aviva’s application with Members.
On 29th
November 2021, we received a late request for
payment of external consultant costs to review the application materials,
despite the fact that the application was submitted in February 2020 and
amendments made on 8th October 2021. This request could have been
made at any stage. Furthermore, we note that the wind microclimate assessment,
which RBC now propose is subject to external review, remains unchanged from the
version submitted in February 2020.
Aviva is not making the appeal
as a bargaining tactic, but as the last resort in the absence of any meaningful
confirmation of RBC’s position on the principle of the development as proposed
and the continued delays. We have repeatedly emphasised the need for the
application to be progressed to determination, as a result of lease expiry
considerations. The urgency to clarify the
future use of the site is only getting more important. It is in light of the
lack of clarity and Aviva’s need to secure a permission to provide certainty in
its future plans for the site, that an appeal is now being progressed.
We note
that in your email of 1st December 2021 you indicated that you would
seek to get the application to the “earliest” planning committee in 2022, but
as this is scheduled for 12th January 2022 this is clearly
impractical, given that the Council’s external consultants are yet to be
appointed. In reality there
has been no clear indication that the application will be determined within a
timescale acceptable to Aviva.
In light
of the above, the decision to appeal for non-determination is entirely
reasonable and the appeal will be submitted shortly.
Kind
regards
Marie
|
From: Conlon, Brian <Brian.Conlon@reading.gov.uk>
Sent: 03 December 2021 15:10
To: Marie Jasper <marie.jasper@bartonwillmore.co.uk>
Cc: Eatough, Richard <Richard.Eatough@reading.gov.uk>
Subject: RE: 200328 - Vastern Court, Caversham Road, Reading (Extension
of time)
Dear Marie,
Many thanks for
clarifying the fact that your client does not
agree to the extension of time request made on the 1st December 2021
and that you intend to respond separately in relation to the independent
financial viability appraisal and daylight/sunlight reviews.
In light of the
above and the fact the Council are currently in the process of considering and
consulting upon a significant amount of revised information submitted to the us
on 8th October 2021 at your request, we would be grateful if you are
able to set out to us your client’s specific reasons for serving a Notice of
appeal against non-determination.
It should be noted
that on the 29th April 2021 you requested the LPA extend the
determination date of this application to July 31st 2021 as a
consequence of ongoing discussions in order to allow the submission of revised
plans. The Council duly agreed on 30th April 2021.
On the 9th
June 2021 (approx. 7½ weeks prior to the expiration of the above agreed EoT)
you confirmed in writing that you were in the process of making revisions to
planning application, including an addendum to the Environmental Statement
(ES). A request was also made to the LPA to confirm the latest position in
relation to cumulative schemes and advise whether there are any additional
schemes we need consider in the revised ES. The LPA responded on the 15th June
2021, acknowledging the fact revision to the planning application were being
made, and provided observations regarding additional schemes to consider in the
revised ES.
On the 11th
June 2021, a revised
Certificate of Ownership Certificate B was submitted to the LPA and attached on
file in anticipation of re-consultation and re-publicity that would occur when
revised information as submitted.
On the 16th
September 2021 (approx.
6½ weeks after the expiration of the agreed EoT), you confirmed that
your team were
finalising the last few reports that would accompany the revised submission.
You confirmed that this has taken your team longer than anticipated due to
workload and summer holidays etc. You also confirmed that the scheme revisions
remained as per earlier discussions held. On the same day, the LPA responded
and acknowledged this update, also taking the opportunity request a
timescale for submission. The answer given was the end of September 2021.
Following the
submission of revised material on the 8th October 2021, the LPA
proceeded to register, upload and reconsult the information submitted. On the
11th October 2021 the LPA
acknowledged
receipt and out of courtesy would notify you when all documents had been
uploaded and relevant consultation actioned. A progress update occurred on the
14th October 2021.
At the time this
Notice of Appeal against non-determination was lodged (30 November 2021), your
client was fully aware that LPA were working on this revised submission
submitted only 7 ½ weeks earlier.
The Council
considers this response wholly unreasonable. Firstly due to the fact that any
delay was caused on the part of the applicant, and secondly the timescales
involved in serving the notice are entirely unrealistic for an LPA to consider,
let alone determine such a significant amount of information pertaining to a
complex major planning application.
As you will be
aware, a Notice of appeal for non-determination should be lodged when there is
no prospect of the LPA determining the application. In this instance,
your client has instructed the submission of a large amount of revised
information, which would imply the expectation that the LPA is permitted
sufficiently reasonable time in order to process, consider and respond to this
request as such. Furthermore, only last week were we provided with verbal
confirmation that your client agrees to pay our appointed daylight
sunlight/microclimate consultants and valuers to consider the FVA only now
submitted with this revised information.
Whilst it is clear
to us that the applicant has caused these delays, the LPA are happy to continue
with the determination of this application and provide a target date for its
determination on the proviso that no new information is submitted, and the
application is determined solely on the basis of the revised information
submitted in October 2021. It would then be LPA’s intention, should the
consideration of this application proceed, to advise of a planning committee
date at our earliest opportunity.
Kind regards,
Brian
Brian Conlon BA Hons MSC
MRTPI
Principal Planner
Planning Section | Directorate for Economic Growth
and Neighbourhood Services
Reading Borough Council
Civic Offices,
Bridge Street,
Reading,
RG1 2LU
01189 373 859 (Ext. 73859)
07855 125 787
Email: brian.conlon@reading.gov.uk
Website | Facebook | Twitter | YouTube
From: Marie Jasper <marie.jasper@bartonwillmore.co.uk>
Sent: 02 December 2021 09:21
To: Conlon, Brian <Brian.Conlon@reading.gov.uk>
Cc: Eatough, Richard <Richard.Eatough@reading.gov.uk>
Subject: RE: 200328 - Vastern Court, Caversham Road, Reading (Extension
of time)
This is an EXTERNAL EMAIL. STOP. THINK before you CLICK links
or OPEN attachments.
Dear
Brian,
In
response to your email below, I write to advise that my client does not agree
to the extension of time request.
The
application was submitted in February 2020, and amended details submitted on 8th
October 2021 (c.8 weeks ago).
We will
respond separately in relation to the independent financial viability appraisal
and daylight/sunlight reviews.
Kind
regards
Marie
|
From: Conlon, Brian <Brian.Conlon@reading.gov.uk>
Sent: 01 December 2021 10:06
To: Marie Jasper <marie.jasper@bartonwillmore.co.uk>
Cc: Eatough, Richard <Richard.Eatough@reading.gov.uk>
Subject: RE: 200328 - Vastern Court, Caversham Road, Reading (Extension
of time)
Dear Marie,
RE: 200328 -
Vastern Court, Caversham Road, Reading
Further to the
Pre-Notification of Intention to Appeal received from CMS law, it is noted that
the agreed determination date for this application expired on the 31st July
2021.
In light of the
recently submitted changes to the application submitted to the Council in
October 2021, the Council considers it reasonable to request an extension of
time to the determination deadline in order to allow time to consider the
impacts of these significant amendments. In particular this extension would
allow the Council time to complete the independent testing of the Financial
Viability Appraisal submitted with these amendments, obtain daylight/sunlight
and microclimate reviews, and allow the application to be scheduled for
determination at the earliest planning committee in the new year following the
conclusion of the above.
The Council thereby
request an extension of time in accordance with Section 34 (2)(c) of the Town
and Country Planning (Development Management Procedure) (England) Order 2015
until 2nd March 2022. I would be grateful if you could confirm in
writing your agreement to this request.
We look forward to
hearing from you.
Best regards,
Brian
Brian Conlon BA Hons MSC
MRTPI
Principal Planner
Planning Section | Directorate of Environment and
Neighbourhood Services
Reading Borough Council
Civic Offices,
Bridge Street,
Reading,
RG1 2LU
The information in this e-mail is confidential to the intended recipient to whom it has been addressed and may be covered by legal professional privilege and protected by law. Reading Borough Council does not accept responsibility for any unauthorised amendment made to the contents of this e-mail following its dispatch.
If received in error, you must not retain the message or disclose its contents to anyone. Please notify us immediately quoting the name of the sender and the addressee and then delete the e-mail.
Reading Borough Council has scanned for viruses. However, it is your responsibility to scan the e-mail and attachments (if any) for viruses.
Reading Borough Council also operates to the Protective Document Marking Standard as defined for the Public Sector. Recipients should ensure protectively marked emails and documents are handled in accordance with this standard (Re: Cabinet Office - Government Security Classifications).
Click
here to report this email as spam.
The information in this e-mail is confidential to the intended recipient to whom it has been addressed and may be covered by legal professional privilege and protected by law. Reading Borough Council does not accept responsibility for any unauthorised amendment made to the contents of this e-mail following its dispatch.
If received in error, you must not retain the message or disclose its contents to anyone. Please notify us immediately quoting the name of the sender and the addressee and then delete the e-mail.
Reading Borough Council has scanned for viruses. However, it is your responsibility to scan the e-mail and attachments (if any) for viruses.
Reading Borough Council also operates to the Protective Document Marking Standard as defined for the Public Sector. Recipients should ensure protectively marked emails and documents are handled in accordance with this standard (Re: Cabinet Office – Government Security Classifications).